Abstract
This paper describes the characteristics of environment of 11kV outdoor distribution substation that was affected to underground cable supply. There is some visual checking and site testing to detect breakdown on the cable and calculated cost involve comparing to suggested solution. Details inspection and testing are usually perform if any tripping or fault occur. In this case, breakdown of insulation cable was studied on how it could be solve with less cost spend. First, inspection and testing was performed in order to find point of fault. Then analysis of data and information was estimated that moisture is the main cause contributes to this case of fault. The affected part was identified so that repairing work could be done. It was confirmed that gear involved in switchgear truck, interconnected bus-bar and insulation of cable was affected and will not be able to operate. Repairing work cost was studied by comparing it with the suggested solution. The suggested solution is to eliminate Sewerage Plant substation from operation supported by availability considered.
Metadata
| Item Type: | Article |
|---|---|
| Creators: | Creators Email / ID Num. Abd Razak, Muhammad Syahmi mie_uitm7@yahoo.com |
| Subjects: | T Technology > TD Environmental technology. Sanitary engineering > Sewerage T Technology > TK Electrical engineering. Electronics. Nuclear engineering > Production of electric energy or power |
| Divisions: | Universiti Teknologi MARA, Shah Alam > Faculty of Electrical Engineering |
| Page Range: | pp. 1-7 |
| Keywords: | Distribution substation, Cable faulty, Repairing maintenance, Moisture |
| Date: | July 2014 |
| URI: | https://ir.uitm.edu.my/id/eprint/103438 |