A visit to 33 kV Stesen Suis Utama (SSU) in UiTM Pulau Pinang

Chan, Hun Beng and Razali, Mazlina and Keria, Roziah and Badrealam, Sabariah and Senin, Syahrul Fithry and Kamarudin, Faizah and Zakariah, Zulfairul and Raja Mohd Noor, Raja Nor Husna (2025) A visit to 33 kV Stesen Suis Utama (SSU) in UiTM Pulau Pinang. Bulletin. Unit Penerbitan PKAPP, UiTM Cawangan Pulau Pinang.
Abstract

On 20 October 2025, the course of Mechanical and Electrical Engineering under the code of program EC223 has organized a visit to the 33kV Stesen Suis Utama (SSU)in UiTM Pulau Pinang, with the consent from the Section of Facility Management, along with the facilitator that explain the almost all its functions to our students.
The 33kV sub-station is the main and primary distribution of power to the whole institution. No access is allowed unless with the consent of relevant authority. The power from TNB is first channeled to the KV sub-station before being distributed to all buildings within the boundary and stepped down as necessary for each structure.
Before entering the building, It is important to visit the transformers available at the back of the substation. There are three transformers, including one unit that functions as a backup. There are 2 types of transformers namely step-up transformer and step-down transformer.
Inside the building is several pieces of equipment that function to distribute power to many locations in the institution. They are the tools between the 33kV and property that ensure the process of power transmissions.
Before the end of the visit, let us have an overview of the schematic diagram of the sub-station. We hope that the visit increases students’ interest in this course and helps them become better civil engineers and project manager in the future.